10/23/2024: Work on the East Side Drainage Improvement Project Package 2 continues to advance steadily on Duke Street between Buffalo Speedway and Wakeforest Avenue. The contractor is actively leveling and installing the upsized reinforced concrete pipes (RCP) between Belmont Street and Brompton Road. Simultaneously, paving crews are working directly behind the storm crew to pave the newly installed roadway.

In addition, another crew has begun roadway demolition on the north side of Rice Boulevard between Wakeforest Avenue and Charlotte Street in preparation for the upcoming paving portion. This work will continue as the crew progresses east towards Kirby Drive.

Rice Blvd between Wakeforest Ave and Charlotte St

                                 Rice Blvd.                                           

We appreciate the community’s patience and cooperation as this project moves forward. Please continue to follow posted traffic signs and detours for your safety. 

For questions, please contact Capital Projects Manager Eduardo Barreto at ebarreto@westutx.gov or 713-662-5848.

_____________________________________________________________________________

10/8/2024: The water shut-off and transfer scheduled for Wednesday, October 9 for the 5800-6100 block of Annapolis St  & 5800-6100 block of Charlotte St. will now take place on Thursday, October 10. The work will begin at 8 a.m. and will last approximately 5-6 hours, with water service restored by the end of the day.

The updated schedule is as follows:

  • Thursday, October 10: 5800-6100 block of Annapolis St. & 5800-6100 block of Charlotte St.

We apologize for any inconvenience and appreciate your understanding as we continue this essential project.

Please contact Capital Projects Manager Eduardo Barreto at ebarreto@westutx.gov or 713-662-5848 with any questions.

_____________________________________________________________________________

10/7/2024: The water shut-off and transfer originally scheduled for Monday, October 14 for the 5800-6100 block of Charlotte St. will now take place on Wednesday, October 9. The work will begin at 8 a.m. and will last approximately 5-6 hours, with water service restored by the end of the day.

The updated schedule is as follows:

We apologize for any inconvenience and appreciate your understanding as we continue this essential project. 

Please contact Capital Projects Manager Eduardo Barreto at ebarreto@westutx.gov or 713-662-5848 with any questions.

_____________________________________________________________________________

10/1/2024: Starting Wednesday, October 2 at 8 a.m., the contractor will begin transferring the old waterline to the newly installed waterline on Rice Blvd. To complete this process, there will be scheduled water shut-offs lasting approximately 5-6 hours. Water service will be restored by the end of the day. The process will begin at the intersection of Lake St. and Rice Blvd., moving one block at a time every other day, weather permitting.

Tentative Shut-off and Transfer Schedule:

  • Wednesday, October 2: 5800-6100 block of Lake St. & 2600 block of Rice Blvd.
  • Monday, October 7: 5800-6100 block of Fordham St.
  • Wednesday, October 9: 5800-6100 block of Annapolis St.
  • Monday, October 14: 5800-6100 block of Charlotte St.

Once the work is completed, crews will flush the lines. Residents are advised to flush their water lines by running water for approximately 30 minutes after service is restored. You may experience brief water discoloration or air in the lines, but the quality of the water will not be affected.

We appreciate your patience and understanding as we work to complete this essential project. For questions, please contact Capital Projects Manager Eduardo Barreto at ebarreto@westutx.gov or 713-662-5848.

_____________________________________________________________________________

On Saturday, September 21, the Contractor will be working between 8 a.m. to 5 p.m. on Rice Blvd. between Wakeforest Dr. and Kirby Dr. The work will include forming the roadway in preparation for pouring concrete. 

Residents should continue to exercise caution around the construction site and abide by all traffic.

If you have questions about this project please contact Capital Projects Manager, Eduardo Barreto by email at  ebarreto@westutx.gov or by phone at 713-662-5848.

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside

_____________________________________________________________________________

9/13/2024: On Monday, September 16, at 9 a.m., water service to homes in the 5900–6100 blocks of Fordham & Annapolis St. will be temporarily shut off to install a new water valve at the southeast corner of Fordham St. and Rice Blvd. The water outage is expected to last 3 – 4 hours. Crews will work diligently to complete the work as quick as possible and restore water service. Inclement weather could postpone work activities to the next day.

During this shut off, crews will also be flushing the lines. Residents may experience brief water discoloration and air in the pipes once service is restored. Please note, that the quality of the water will not be affected.

If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at ebarreto@westutx.gov or by phone at 713-662-5848.

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside. 

_____________________________________________________________________________

9/11/2024 12 p.m. – On Thursday, September 12, at 8 a.m., water service to homes in the 5900–6100 blocks of Fordham St. will be temporarily shut off to install a new water valve at the southeast corner of Fordham St. and Rice Blvd. The water outage is expected to last 3 – 4 hours. Crews will work diligently to complete the work as quick as possible and restore water service. Inclement weather could postpone work activities to the following week.

During this shut off, crews will also be flushing the lines. Residents may experience brief water discoloration and air in the pipes once service is restored. Please note, that the quality of the water will not be affected

If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at ebarreto@westutx.gov or by phone at 713-662-5848.

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside. 

_____________________________________________________________________________

9/6/2024 at 12:55 p.m. – The contractor will not be working as originally planned on Saturday, September 7. Work will proceed normal operations Monday, September 9.

For more information about the Eastside Drainage and Roadway Project, residents can visit the project’s dedicated webpage at www.westutx.gov/eastside.

Those with specific questions or concerns are encouraged to contact Capital Project Manager Eduardo Barreto at 713-662-5848 or via email at ebarreto@westutx.gov.

_____________________________________________________________________________

9/5/2024: Water service has been restored to the 6000 – 6100 blocks of Annapolis & Fordham. 

5:17 p.m.: Water service is temporarily interrupted on the 6000-6100 blocks of Annapolis & Fordham to complete a waterline repair. Repairs are estimated to take up to 4 hours.

If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at ebarreto@westutx.gov or by phone at 713-662-5848.

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside

_____________________________________________________________________________

On Thursday, September 5, starting at 8 a.m., the intersection of Fordham St. and Rice Blvd. will be temporarily closed for approximately 3-4 hours. This closure is necessary for the contractor to install a new waterline across Rice Blvd. Once the installation has been completed, the intersection will be reopened to traffic.

Additionally, the contractor will return on Saturday, September 7, to work on Rice Blvd. and Duke St. Crews will work between 8 a.m. to 5 p.m. We appreciate your patience and understanding and encourage residents to plan their routes accordingly. Please adhere to all posted signs and detours for your safety.

For more information about the Eastside Drainage and Roadway Project, residents can visit the project’s dedicated webpage at www.westutx.gov/eastside. 

Those with specific questions or concerns are encouraged to contact Capital Project Manager Eduardo Barreto at 713-662-5848 or via email at ebarreto@westutx.gov.

_____________________________________________________________________________

8/29/2024: Water service has been restored to the 6000 – 6100 blocks of Annapolis. 

11:47 a.m. – Water service is temporarily interrupted on the 6000-6100 blocks of Annapolis to complete a waterline repair. Repairs are estimated to take 4 – 6 hours. The intersection of Annapolis & Rice Blvd. will be temporarily closed and will reopen at the end of the day.  

Residents are reminded to exercise caution around the construction site and to abide by all traffic laws. Drivers should plan their travel routes accordingly and expect delays. Thank you for your understanding and patience.

If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at ebarreto@westutx.gov or by phone at 713-662-5848.

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside. 

 _____________________________________________________________________________

8/27/2024: Starting today, August 27, the intersection of Duke Street and Vanderbilt Street will be closed for a minimum of 3 to 4 weeks to facilitate the construction of the underground storm sewer. We ask that all drivers and pedestrians take alternative routes during this period and strictly adhere to traffic signs following the detour route. 

Detour Route: Traffic normally flowing west through Duke Street will be redirected to Belmont Street. From Belmont Street, drivers will be guided to turn onto Pittsburg Street to reach their intended destinations on the other side of the closure. Vanderbilt Street traffic will be diverted onto Pittsburg Street, providing access around the closed intersection. Your cooperation is essential for the smooth progression of ongoing paving and drainage improvements in the area and for maintaining safety in the community. Thank you for your understanding and patience.

If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at ebarreto@westutx.gov or by phone at 713-662-5848.

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside. 

_____________________________________________________________________________

8/23/2024: The Contractor, TB Construction, is making progress on multiple fronts as part of the ongoing Eastside Paving & Drainage Improvement Project Package 2. Crews are currently installing a new junction concrete box at the intersection of Vanderbilt St. and Duke St. the work is expected to take a minimum of 2-3 weeks to complete.

On Rice Blvd, crews have bored approximately 1,000 linear feet of waterline and are now paving the southside of the 2700 block roadway. This work is crucial for upgrading the area’s infrastructure and is expected to continue over the coming weeks.

During this time, traffic control measures remain in effect. The 2800–3100 blocks of Duke Street are reduced to one westbound lane, with a detour route south on Buffalo Speedway, east on Pittsburg, and north on Wakeforest. And at Rice Blvd. The traffic pattern is reduced to one westbound lane from Kirby Dr. to Wakeforest Ave. Drivers traveling eastbound to Kirby Dr. will detour south down Wakeforest Ave., east on University Blvd., to then continue their route.

IMG_7684IMG_7687

                                 Vanderbilt & Duke                                                                                                   Rice Blvd

Residents are reminded to exercise caution around the construction site and to abide by all traffic laws. Drivers should plan their travel routes accordingly and expect delays. City staff will continue to work with the contractor to mitigate impacts whenever possible.

Your cooperation and patience are greatly appreciated as we work to improve the city’s infrastructure.

If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at ebarreto@westutx.gov or by phone at 713-662-5848.

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside.  

_____________________________________________________________________________

8/2/2024: Beginning the week of Monday, August 5, the contractor (TB Concrete Construction) will set up traffic control for the installation of the new waterlines on Rice Blvd. between Wakeforest Ave. and Kirby Dr. Construction activities will begin on Rice on Tuesday, August 6, weather permitting.

Traffic – The traffic pattern will be reduced to one westbound lane from Kirby Dr. to Wakeforest Ave. Drivers traveling eastbound to Kirby Dr. will detour south down Wakeforest Ave., east on University Blvd.,  to then continue their route. 

Residents should continue to exercise caution around the construction site and abide by all traffic laws. Drivers should plan their travel routes accordingly and expect delays. City staff will continue to work with the contractor to mitigate impacts whenever possible.

If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at ebarreto@westutx.gov or by phone at 713-662-5848.

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside. 

_____________________________________________________________________________

7/26/2024:Beginning the week of Monday, July 29, the contractor (TB Concrete Construction) will begin work in the 2900 – 3000 blocks of Duke. 

The contractor will begin in this section by removing the pavement in 800 feet sections. Once removed, the existing storm sewer pipe will be replaced with a larger storm sewer pipe. At the end of this process, the roadway will then be repaved.   

Driveway Access: During certain periods of construction, driveway access to identified properties within the active work zone will be impacted during the day. Residents will be provided with temporary driveway access at the end of each workday. All identified driveway aprons will be removed and replaced with a light broom finish. No pigment, color, tile, brick, or patterning shall be placed or installed by the City’s contractor. Prior to the removal of driveways, notification will be provided to each affected resident ahead of time, so that cars can be removed from garages and driveways.

Residents should continue to exercise caution around the construction site and abide by all traffic laws. Drivers should plan their travel routes accordingly and expect delays. City staff will continue to work with the contractor to mitigate impacts whenever possible.

If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at ebarreto@westutx.gov or by phone at 713-662-5848.

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside.  

________________________________________________________________________________________

5/10/2024: Beginning Monday, May 13, TB Concrete Construction, will mobilize and begin the installation of traffic control and tree protection along the 2800 – 3100 blocks Duke St. for the East Side Paving & Drainage Improvement Project Package Two (2). 

Starting on Monday, May 20, TB Concrete Construction will break ground on Section One of the Project and begin removing existing pavement on the south side of Duke St.

Package Two is split into 3 sections.

  • Section One: Removal of the pavement and storm sewer pipe upsizing followed by paving the roadway at the 2800 – 3100 blocks of Duke St. 
  • Section Two: Removal of the pavement, storm sewer pipe upsizing, and installation of new waterline followed by paving the roadway at the 2600 & 2700 blocks of Rice Blvd. 
  • Section Three: Removal of the pavement and storm sewer pipe upsizing followed by paving the roadway at the 5800 – 6400 blocks of Wakeforest Ave. 

During each section, the contractor will begin by removing the pavement in 800 feet sections. Once removed, the existing storm sewer pipe will be replaced with a larger storm sewer pipe. At the end of this process the roadway will then be repaved.   

Traffic Control: The 2800 – 3100 Blocks of Duke will be reduced to one westbound lane. Drivers will detour south down Buffalo Speedway, east on Pittsburg, and then north on Wakeforest to then continue West. 

Driveway Access: During certain periods of construction, driveway access to identified properties within the active work zone will be impacted during the day. Residents will be provided with temporary driveway access at the end of each workday. All identified driveway aprons will be removed and replaced with a light broom finish. No pigment, color, tile, brick, or patterning shall be placed or installed by the City’s contractor. Prior to the removal of driveways, notification will be provided to each effected resident ahead of time, so that cars can be removed from garages and driveways.

Residents should continue to exercise caution around the construction site and abide by all traffic laws. Drivers should plan their travel routes accordingly and expect delays. City staff will continue to work with the contractor to mitigate impacts whenever possible.

If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at ebarreto@westutx.gov or by phone at 713-662-5848.

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside. 

 

_________________________________________________________________________________

4/24/2024: Package One of the East Side Paving & Drainage Improvement Project is nearing completion. A town hall meeting is scheduled as construction for Package Two is anticipated to begin in May 2024. Engineers and city staff will provide a presentation about the project, review exhibits, and answer questions during the town hall meeting.

  • DATE: Tuesday, April 30, 2024
  • TIME: 6:00 – 8:00 p.m.
  • VENUE: West University Community Building/Senior Services Auditorium
  • ADDRESS: 6104 Auden Street, West University Place, TX 77005

Package Two will include paving and drainage upgrades along Wakeforest Avenue from Plumb Street to Pemberton Street, Rice from Wakeforest to Kirby Dr., and Duke Street from Buffalo Speedway to Wakeforest.

If you are unable to attend the meeting but would like to provide comments, you may submit your comments via email to eastside@westutx.gov. All comments must be submitted by Tuesday, May 14, 2024. (Please reference Eastside Paving and Drainage Project in the subject line)

Additionally, we would like to gather information from residents with special needs who may be affected throughout the project. We have created an online form for residents to provide information and identify their special needs requests. You can find this form by visiting: www.westutx.gov/specialrequest.   Special requests must be submitted by Friday, May 10.

For any inquiries or concerns regarding this project, please feel free to contact Capital Project Manager Eduardo Barreto at 713-662-5848 or via email at ebarreto@westutx.gov.  

To sign up to receive news and updates on the Eastside Paving and Drainage Improvement Project or for more information, please visit www.westutx.gov/eastside. 



Source link

News service powered by houstonrealestate.co

Featured Properties

share this ARTICLE:

Facebook
Twitter
Pinterest
WhatsApp
LinkedIn